Scoil Caitlin Maude, Tallaght

Scoil Caitlin Maude, Tallaght

Project: Scoil Caitlin Maude, Tallaght
Client: Department of Education and Skills – Rapid Schools Programme
Services: Assigned Certifier
Architect: Oppermann Associates
Main Contractor: Western Building Systems
Completion: April 2016


MLM Ireland are appointed as Assigned Certifier by DoES under the Rapid Schools Programme. This project consists of the construction of a new 16 classroom school with a SET facility and associated siteworks at Scoil Caitlin Maude, Tallaght, Co. Dublin. The school is to contain a GP Hall, a library / resource room and other ancillary accommodation. The siteworks include for all soft and hard play areas, 2no. ballcourts, foot and cycle paths, bicycle shelters, boundary treatments, pedestrian and vehicle access roads, car parking and landscaping. The construction period is 38 weeks.